New Connection
MEPCO has now made the process easy and transparent for the installation of new electric meter connections in Multan or any other South Punjab district. For domestic, commercial, or industrial connections, you can now submit an MEPCO online meter application, receive your demand notice, and track its status easily.
Documents Required for New Connection
Before applying, make sure you have the following documents ready:
- Copy of CNIC (applicant/owner)
- Proof of ownership or tenancy agreement
- Attested affidavit confirming no arrears
- Wiring contractor test report
These documents are mandatory to process your new meter connection request.
How to Apply for MEPCO New Meter Connection
The process to apply is straightforward:
- Fill out the MEPCO new connection form (available online or at offices).
- Attach all required documents.
- Submit your application at the nearest MEPCO Customer Service Center or through the online portal.
- Receive your MEPCO demand notice (payment slip).
- Pay the demand notice at the designated bank.
- Once verified, your new meter connection will be installed.
This ensures a smooth and transparent process for all MEPCO consumers.
MEPCO Demand Notice & Tracking
A demand notice is an official slip issued by MEPCO that includes the new electricity connection fee and meter installation charges. After submission of your application, MEPCO generates this notice, which you must pay to proceed.
You can easily:
- Check the MEPCO demand notice online
- Track the WAPDA demand notice through the official portal
- Confirm payment status before installation
This step is important, as MEPCO will only install the meter after successful demand notice payment.
New Electricity Connection Fee & Meter Price in Pakistan
The new electricity connection fee depends on the type of connection:
- Domestic (residential households)
- Commercial (shops, offices, small businesses)
- Industrial (factories, large-scale units)
The charges include meter installation, security deposits, and service fees. While the electric meter price in Pakistan and the energy meter price in Pakistan vary, MEPCO provides updated rates through demand notices to ensure accuracy.
Estimated Time for New MEPCO Connection
The duration depends on your connection category and load requirement. MEPCO follows a structured timeline for processing applications:
Category 1 – Up to 15 kW (Domestic & Small Commercial)
Total Expected Time: Around 30 days
| Step | Process | Estimated Days |
| 1 | Submit application form with documents → get receipt & seniority number | 1 |
| 2 | Site visit by MEPCO officer to check the feasibility | 3 |
| 3 | Cost estimation prepared | 2 |
| 4 | Demand notice issued | 2 |
| 5 | Applicant pays the demand notice & submits the receipt | 2 |
| 6 | Wiring test report submitted & verified | 3 |
| 7 | Priority list updated by the office | 1 |
| 8 | Service Connection Order (SCO) issued | 3 |
| 9 | Store requisition for meter & installation material | 3 |
| 10 | The store provides items to the field office | 5 |
| 11 | Meter installation & final connection | 5 |
Category 2 – 16 to 70 kW (400 Volts)
The process is similar to Category 1 but may take up to 44 days due to higher load and verification.
Category 3 – 71 to 500 kW (400 Volts, Large Commercial & Industrial)
This category requires more approvals and equipment allocation. The process can take up to 73 days from application submission to installation.
MEPCO Bill Registration After New Connection
Once your new meter is installed, you’ll receive a MEPCO reference number printed on your first bill. This reference number is required for:
- MEPCO bill registration
- Checking and downloading bills online
- Subscribing to SMS or email alerts
This helps you stay updated on your monthly usage and payments.
FAQs
How long does it take to get a new MEPCO connection?
The process takes a few weeks after the demand notice, payment, and verification.
Can I apply online for a MEPCO new meter?
Yes, MEPCO offers an online meter application service through its official portal.
How do I pay my MEPCO demand notice?
You can pay through designated banks, online banking apps, Easypaisa, or JazzCash.
What is the fee for a new electricity connection?
Charges vary for the domestic, commercial, or industrial category. The official demand notice provides exact details.
